ATC Kenya Operations Limited v Telkom Kenya Limited (Civil Case E096 of 2022) [2023] KEHC 26183 (KLR) (Commercial and Tax) (30 November 2023) (Ruling)
Neutral citation:
[2023] KEHC 26183 (KLR)
Republic of Kenya
Civil Case E096 of 2022
JWW Mong'are, J
November 30, 2023
Between
ATC Kenya Operations Limited
Plaintiff
and
Telkom Kenya Limited
Defendant
Ruling
1.On 27th April 2022, the Defendant filed a Chamber Summons under Section 6 of the Arbitration Act, Rule 2 of the Arbitration Rules, 1997, seeking the following orders: -1.That this Honourable Court be pleased to stay further proceedings in this matter pending arbitration.2.That the suit be referred to an Expert and Arbitrator by the London Court of International Arbitration (“LCIA") accordance with the terms of the Master Site Licence Agreement dated 1st October 2018 between the Plaintiff and the Defendant, the Master Tower Agreement dated 12th August 2014, Site Sharing Agreement dated 25th November 2009 ("the Tower Agreements").3.That costs of this Application be provided for.
2.The application is supported by the grounds on its face and the supporting affidavit sworn by Esther Kihihia on 27th April 2022. Through the Master Site Licence Agreement dated 1st October 2018, the Master Tower Agreement dated 12th August 2014 and Site Sharing Agreement dated 25th November 2009 (“the Tower Agreements”), the Plaintiff and its predecessors in title provided the Defendant with telecommunication infrastructure services for a fee. The Plaintiff was obligated to provide licensed spaces for installation, maintenance and operation of the Defendant’s towers, apparatus and communication equipment as well as operation and maintenance services.
3.Through the Master Site Licence Agreement, the Defendant transferred several sites to the Plaintiff and licensed a portion of each of the sites back to from the Plaintiff at a fee. By a Plaint dated 24th March 2022, the Plaintiff filed this suit against the Defendant for specific damages of USD2,643,176.35 and Kshs.611,074,576.89/- for unpaid invoices due for licensing fees running from 2021.
4.According to the Defendant, the Plaintiff’s claims have no basis and are highly disputed as it incurred huge losses due to the Plaintiff’s failure to carry out restoration works following outages, disconnecting and allowing obstruction of its apparatus in breach of the Tower Agreements. It also contends that the money claimed by the Plaintiff is with respect to invoices have been either been already offset or settled and/or invoices not shared with it. It further contends that it has been paying the sum of Kshs.150 million per month which the Plaintiff has not pleaded nor acknowledged.
5.For these reasons, the Defendant asserts that the dispute ought to be referred to arbitration pursuant to clauses 11.5 as read together with Clauses 21, and 22.12 of the Master Site Licence Agreement, Clause 20.3 of the Master Tower Agreement and Clause 19.1 of the Site Sharing Agreement.
6.In response, the Plaintiff filed a preliminary objection (PO) dated 23rd May 2022 grounds that the instant application is fatally defective and ought to be struck out because it was filed on 11th May 2022, 16 days after entering an unconditional appearance on 30th March 2022, contrary to section 6 of the Arbitration act. The Plaintiff also filed a Grounds of Opposition dated 18th June 2023, on the grounds that there is no dispute to be referred to arbitration as the Defendant has admitted the debt due to it and has failed to comply with the contractual mechanism for challenging the debt.
7.Both the application and the PO were canvassed by way of written submissions. The Defendants filed written submissions dated 21st August 2023 while the Plaintiff filed written submissions dated 20th September 2023.
Analysis And Determination
8.I have considered the pleadings filed by the parties in this matter and their written submissions. The issue for determination is whether the Defendant has made out a case for stay of these proceedings and referralof the dispute to arbitration.
9.Section 6 of the Arbitration Act provides that:-
10.The principles for consideration in such an application were succinctly captured the oft-cited decision in Niazsons (K) Ltd v China Road Bridge [2001] KLR, as follows:-
11.As to the first condition to be satisfied, according to the Plaintiff, the instant application is fatally defective and ought to be struck out as the Defendant only filed its application to refer the dispute to arbitration on 11th May 2022, 16 days after entering an unconditional appearance on 21st April 2022.
12.It is manifest from the record that indeed the present application was filed 16 days after entry of appearance. Following the 2009 amendment to the Arbitration act, Section 6 (1) of the Act requires that a party files an application for stay of proceedings not later than the time when that party enters appearance. In Eunice Soko Mlagui v Suresh Parmar & 4 others (Civil Appeal No. 276 OF 2014) [2017] eKLR, the Court of Appeal while interpreting the 2009 amendment to Section 6 of the Act vis a vis the previous provision, confirmed that: - “After 2009, the provision still requires a party to apply for referral of the dispute to arbitration at the time of entering appearance or before acknowledging the claim in question.
13.In SBI International Holdings (Kenya) v Kenya National Highway Authority (Case No. E075 of 2020) [2020] eKLR, the Court, faced with circumstances similar to the present case, stated as follows:-
14.Guided by the above decisions, I find that the Defendant was entitled to file the application to stay proceedings before taking any further steps acknowledging the Plaintiff’s claim. Since the Defendant had not filed any defence or taken any steps which would construed as acknowledging the Plaintiff’s claim, the application for stay and reference to arbitration is properly before the court. The Preliminary Objection lacks merit and is dismissed with costs.
15.As regards the second and third conditions, the Defendant relied on Clauses 21, and 22.12 of the Master Site Licence Agreement, Clause 20.3 of the Master Tower Agreement, and Clause 19.1 of the Site Sharing Agreement for the submission that there are valid and binding arbitration agreements between the parties and that there is in fact a dispute between the parties with regard to the matters agreed to be referred to arbitration. It placed reliance on Euromec International Limited v Shandong Taikai Power Engineering Company Limited (Civil Case E527 of 2020) [2021] eKLR.
16.On its part, the Plaintiff submitted that there is no dispute between the parties to be referred to arbitration because its claim is for a specific and liquidated claim which is readily ascertainable from the pleadings and that the Defendant’s application is only meant delay payment of the indisputable debt. The Plaintiff faulted the Defendant for not referring any dispute to arbitration in accordance with the contracts, before this suit was filed. The Plaintiff elaborated that pursuant to clauses Clauses 11.1.1, 11.1.2, 11.5 and 11.5 (d) of the Master Site Agreement and Clause 6.4 of the Master Tower Agreement, the Defendant was required to either pay all invoices or notify it of the disputed portion of the invoice with detailed reasons within 30 days of receipt. The Plaintiff thus asserted that a dispute regarding invoices could only be referred to an Expert under Clause 21 if the parties failed to reach agreement on the disputed amounts within 30 days.
17.The Plaintiff also argued that the debt has been admitted by the Defendant in the past. Through an email dated 19th November 2021, the Defendant's CEO, Mr. Mugo Kibati admitted the indebtedness and offered to pay of Kshs. 2.7 Billion over a period of 18 months at Kshs. 150 Million per month. Again, through a letter dated 7th March 2022, Mr. Kibati did not dispute the debt but acceded that the parties were in discussions over the settlement of amounts owed. The Plaintiff relied on Mustill & Boyd Commercial Arbitration (1st ed, Butterworths, London, 2001) at 96 to argue that since the Defendant agreed that money was due, there is no dispute to be referred to arbitration, rather the suit should proceed.
18.In my assessment, both parties confirm that there was a valid and binding arbitration agreement between them. The issue in contest is whether there exists a dispute that was agreed to be referred to arbitration.
19.Clauses 11.1.1, 11.1.2, 11.5 and 11.5 (d) 21 and 22.12 of the Master Site License Agreement provide for internal dispute resolution mechanism within the agreements referred hereto and specifically clause 22.12 of Master Site License Agreement provides as follows:-
20.Similarly Clause 20.3 of the Master Tower Agreement, provide as follows:-
21.From the above, it is clear that the parties agreed to resolve disputes through arbitration where their attempts at amicable settlement informally through discussions failed. In this matter, the dispute relates to payment of invoices issued by the Plaintiff for licensing fees with respect to sites for its towers, apparatus and communication equipment.
22.From the record, it is manifest that there was a dispute between the parties with respect to unsettled invoices for licensing fees. The agreement between the parties clearly outlines how the disputes arising thereto would be resolved and parties agree that if they cannot internally agree to resolve the dispute the same would be referred to arbitration as per clause 20.3 of the agreement.
23.Consequently, I am satisfied that the application to stay the proceedings and refer the matter to arbitration has merit and I shall allow the same. Parties will proceed as per clause 20.3.5 of the agreement herein. Each party will bear its own costs of this application.It is so ordered.
DATED, SIGNED AND DELIVERED VIRTUALLY AT NAIROBI THIS 30th DAY OF NOVEMBER, 2023.………………………………………..J.W.W. MONG’AREJUDGEIn the Presence of:-Ms. Kahora for the Plaintiff/Respondent.Mr. Nyaburi for the Defendant.Amos - Court Assistant