Karago & Associates Architects Limited & 11 others v Kenya Hospital Association also referred to as the Nairobi Hospital (Miscellaneous Application E515 of 2021) [2022] KEHC 13336 (KLR) (Commercial and Tax) (16 September 2022) (Ruling)
Neutral citation:
[2022] KEHC 13336 (KLR)
Republic of Kenya
Miscellaneous Application E515 of 2021
A Mshila, J
September 16, 2022
Between
Karago & Associates Architects Limited
1st Applicant
Karkan Partership Ltd
2nd Applicant
Tardem & Stark Ltd
3rd Applicant
Civil Engineering Design (K) Ltd
4th Applicant
BKPMG Health Solutions PVT Ltd
5th Applicant
Maiteri & Associates
6th Applicant
Norkun Intakes Ltd
7th Applicant
Geomax Engineers
8th Applicant
Atkins (previously Howard Humphreys EA Ltd)
9th Applicant
Interconsult Engineers Ltd
10th Applicant
Karago Engineers Ltd
11th Applicant
Jelani Interior Designers
12th Applicant
and
Kenya Hospital Association also referred to as the Nairobi Hospital
Respondent
Ruling
1.The applicants filed a notice of motion dated July 2, 2021 brought under Rule 7 of the Arbitration Rules, 1997 and Section 35 of the Arbitration Act. The application was supported by the sworn affidavit of Joseph Karago and the Applicants sought for orders that;a.Pending the hearing and determination of this Application, there be a stay of execution of the Interim Award published by the Arbitral Tribunal constituted by the Hon Calvin Nyachoti, the sole arbitrator, on June 13, 2021, and as further amended on 2June 8, 2021, and/or any further proceedings in respect of the award.b.Pending the hearing and determination of this Application, there be a stay of the arbitral proceedings before the Arbitral Tribunal constituted by the Hon Calvin Nyachoti, the sole arbitrator.c.The Interim Award published by the Arbitral Tribunal on June 13, 2021, and as further amended on June 28, 2021, be set aside in its entirety or as the Court may deem fit.d.The Court to grant such other relief as it may deem fit and just.e.The costs of and incidental to this Application be provided for.
Applicants’ case
2.It was the Applicants’ case that the interim award dealt with a dispute not contemplated by or not falling within the terms of the reference to arbitration. This is because the tribunal had ordered parties to conduct a joint verification, take an inventory and re-measure all the works with respect to all the projects that the applicants undertook with the respondent, in order to determine the value of the construction works done by the different contractors executing those serial and independent projects. Whilst the dispute by the applicants is for determination of fees payable to them upon the termination of their services by the respondent and not on the value of the construction works executed by third parties, that would be the building contractors.
3.They further stated that the interim award seeks to re-write the contract between the parties, which action is in conflict with the public policy of Kenya. This is because despite parties having agreed, under the Model Service Agreement, on how to determine fees payable upon the termination of the applicants services, the tribunal is forcing parties to engage in a dispute resolution process that they did not agree to.
4.By the tribunal ordering a re-measurements and verification process in a Consultancy Agreement, it totally deviates from the usages of the trade practices applicable to the construction industry.
5.In their submissions, the applicants submitted on the issue of whether the Interim Award published on June 13, 2021, and as further clarified/amended on June 28, 2021 ("Interim Award"), offends the provisions of Section 35 of the Arbitration Act. It was also the applicants’ submission that the arbitral tribunal failed to decide the notice of motion application dated January 27, 2021, in accordance with the terms of the model service agreement.
6.Coincidentally, in the interim award, the arbitral tribunal concurs with the applicants herein that the re-measurement process is un-contractual having not been provided for in the model service agreement but goes ahead to grant the orders sought for in the notice of motion application dated January 27, 2021.
7.The applicants relied on the decision in Kenya Agricultural and Livestock Research Organization (formerly Kenya Agricultural Research Institute) v Njama Ltd [2017] eKLR where the court stated as follows:
8.The applicants further submitted that the interim award seeks to re-write the contract between the parties, which action is in conflict with the public policy in Kenya. This is because despite parties having agreed, under the Model Service Agreement, on how to determine fees payable upon termination of the applicants services (See: Clause 35 of the Model Service Level Agreement), the tribunal is forcing parties to engage in a dispute resolution process that they did not agree to.
9.Further the interim award orders parties to use a process that is not recognized in the construction industry to determine a dispute touching on the fees payable to the applicants. The Orders direct parties, to undertake the valuation of construction works process without involving the building contractors who undertook those works. This process goes against the provisions of Section 29 (5) of the Arbitration Act which provides that,
10.It was the applicant’ argument that the actions of the Hon. Arbitrator Calvin Nyachoti are clearly an attempt to re-write the contract between the parties and is therefore in conflict with the public policy in Kenya (See: Christ for all Nations v Apollo Insurance Co Ltd [2002] EA 366 and Rwama Farmers’ Co-operative Society Ltd v Thika Coffee Mills Ltd [2012] eKLR)
11.The applicants added that the interim award is impossible to implement and touches on the rights of third parties who are not party to the arbitral proceedings. The construction sites are in the possession of the respondent, and therefore, the applicants have nothing else to hand over.
12.It was also the applicants’ position that the clarification of the interim award creates further ambiguity and contradictions arising from the interim award. The arbitral tribunal acknowledged that it is not in a position to ascertain which projects/works/payments are disputed as parties are yet to file their pleadings yet proceeds to issue directions on the re-measurement of all projects undertaken by the applicants since the applicants signed the Model Service Agreement without considering whether or not the applicants have any dispute on all those projects, which would clothe him with jurisdiction over those contracts. The Arbitrator nevertheless decided without any basis that all the projects are in dispute.
13.In setting aside, the interim award by Hon. Arbitrator Calvin Nyachoti, the applicants asked the Court to bear in mind the decision of APA Insurance Co Ltd v Chrysanthus Barnabas Okemo [2005] eKLR, while considering an application to set aside an arbitral award under Section 35 of the Act the court rendered itself thus:
respondent’s case
14.In response to the applicants’ application, the respondent stated that as a preliminary issue, the applicant failed to disclose before the court that there was no jurisdictional challenge before the Arbitrator and that the application whose award the applicant seeks to set aside is an application for joint verification, taking of inventory and re-measurement of works. According to Section 17 of the Arbitration Act, 1995, the question of jurisdiction ought first to have been brought before the Arbitral Tribunal.
15.The principles elucidated above refer to the doctrine of Kompetenz Kompetenz which is a cardinal principle of arbitration law and practice. From the foregoing, it is apparent that the court lacks the requisite jurisdiction to determine the question on the scope of the Arbitrator's jurisdiction and for this reason alone, this ground for setting aside of the Award ought to fail. The applicant cannot be heard to raise jurisdictional questions for the first time at this stage and in this forum.
Issues For Determination
16.After considering the applicants’ and the respondent’s case the court has framed the following issues for determination;a.Whether the Interim Award dealt with issues not falling within the terms of the reference to arbitration.b.Whether the interim Award should be set aside for offending public policy.
Analysis
17.It is trite law that the role of the Court in arbitration matters is only supervisory, and its jurisdiction may only be invoked in very specific situations as stipulated in the Act. Section 10 of the Arbitration Act provides: -
18.By this section, the jurisdiction of the Court is limited and restricted and may only be invoked in very clear circumstances specified under the Act. Further, Section 32A of the Arbitration Act provides: -
19.The parties herein referred their dispute to the arbitrator pursuant to and in accordance with the provisions of clause 44 of the particular conditions of the model service level agreement which contains the arbitration agreement.
20.The applicants’ case is that the Interim Award dealt with a dispute not contemplated by or not falling within the terms of the reference to arbitration. They argued that the tribunal had ordered parties to conduct a joint verification, take an inventory and re-measure all the works with respect to all the projects that the applicants undertook with the respondent, in order to determine the value of the construction works done by the different contractors executing those serial and independent projects.
21.In the applicants’ opinion the dispute by the applicants is for determination of fees payable to them upon the termination of their services by the respondent and not on the value of the construction works executed by third parties, being the building contractors. The Interim Award seeks to re-write the contract between the parties, which action is in conflict with the public policy of Kenya. Despite parties having agreed, under the Model Service Agreement, on how to determine fees payable upon the termination of the applicants services, the tribunal is forcing parties to engage in a dispute resolution process that they did not agree to.
22.The respondent on the other hand maintained that as a preliminary issue, the applicant failed to disclose before the court that there was no jurisdictional challenge before the Arbitrator and that the application whose award the applicant seeks to set aside is an application for joint verification, taking of inventory and re-measurement of works.
23.Section 35 of the Arbitration Act stipulates as follows on the subject of setting aside arbitral awards:
24.Simply put, the applicants herein sought to have the arbitral award set aside the Arbitral award for reasons that;a.The award dealt with issues that were outside the scope of the arbitration agreement.b.The award was inimical to the precepts of public policy.
25.Black’s law Dictionary defines public Policy as follows:
26.In Glencore Grain Ltd v TSS Grain Millers Ltd [2002] 1 KLR 606, it was held:
27.In Christ for all Nations vs Apollo Insurance Co Ltd. (2002) EA 366 Ringera J (as he then was) explained the scope of public policy as a ground for setting aside an arbitral award as follows:
28.In Mall Developers Limited vs Postal Corporation of Kenya ML Misc. No. 26 of 2013 [2014] eKLR the court observed that:
29.It is therefore important when determining whether the Arbitrator in the instant case went beyond the matters under reference, to examine terms of the Agreement between the parties in relation to the dispute referred to arbitration.
30.It is not in dispute that the professional fees as set out in Appendix C1 of the Particular Conditions of the Mode Service Level Agreement provided;
31.The respondent in its submissions went on to state that the applicants’ fees is directly measured from the value of works as outlined in the Architects and Quantity Surveyors Act, cap 525 which governs the applicants’ profession under the fifth schedule on the conditions of engagement and scale of professional charges for quantity surveyors which provides;
32.The applicants highlighted clause 35 of the model service level agreement in opposition to the arbitrator’s directive to take an inventory and re-measure all works with respect to the projects that the applicants undertook with the respondent in order to determine the value of the construction works done by the different contractors executing those serial and independent projects. The said Clause 35 stipulates as follows:
33.In rebuttal, the respondent argued that it challenged the certificates produced by the applicants and for this reason invited the applicants for a joint audit of works to ascertain and verify the extent of works undertaken in order to settle the actual fees due to the applicants. That it was for this reason that the arbitrator allowed the application by the respondent for re-measurement of works.
34.An excerpt of the impugned interim award reads as follows;
35.The import of the above is that, whereas the arbitrator acknowledged the provisions and terms of the parties’ agreement; there was an impasse borne out of the technical audit report, the final accounts and the disputed certificates, which audit reports were prepared in accordance with clause 35 of the model service level agreement.
36.It is the Court’s understanding that at Paragraphs 63 and 64 the Arbitrator stated that the exercise was meant to solve the puzzle the parties found themselves in and in the event the exercise does not solve the issue, “the Tribunal and parties alike shall be in a position to better ventilate their claims and narrow down issues for determination by the Tribunal.”
37.It is the Court’s considered view therefore that the Arbitrator’s directive is meant to make the issues for determination of the main dispute clearer and the Arbitrator is yet to fully determine the dispute at hand. It is therefore premature for the applicants to contend that the Interim Award does not fall within the terms of the reference to arbitration or that it is against public policy and it would be prudent for the applicants to allow the Arbitrator time to determine the dispute.
Findings and determination
Orders Accordingly.
38.For the foregoing reasons this court makes the following findings and determinations;i.The application is found to be unmerited and it is hereby dismissedii.The costs to abide the outcome of the Final Award.iii.The matter is referred back to Arbitration
DATED SIGNED AND DELIVERED AT NAIROBI THIS 16TH DAY OF SEPTEMBER, 2022.HON. A. MSHILAJUDGEVirtually in the presence of: -Lucy: Court AssistantMr Davidson Makau: Advocate for the applicantJoy Anami holding brief for Dr Mutubwa: Advocate for the respondent